ITEM

Projects

Employer

Engineering Co

Duration

(Days)

Progress

Contract Start Date

Pipe Length

(KM)

1
Construction of 14" Oil Transmission Pipeline Rey-Ghoochak
NIOEC
NIOEC
270
in execution
2006/6/20 48
2
Engineering , Procurement  and Constructon (EPC) 36" TABRIZ-MIANDOAB    (phase 1)
East Azarbijan Province
NILPAY Engineering co.
500
finished/delivered
2005/7/27 84
3
Gas Distribution and branches (LAMERD City)
NIGC Fars Province
NIGC - Fars Province
450
finished/delivered
2005/5/1 220
4
MOJEN-SHAHROOD transfer pipeline and related branches (PC)
NIGC Semnan
NIGC - Shahrood Province
350
finished/delivered
2003/6/21 42
5
BONAB transfer pipeline and distribution
NIGC (east Azarbijan)
NIGC (east Azarbijan)
360
finished/delivered
2004/3/4 50
6
SHABESTAR
NIGC (east Azarbijan)
NIGC (east Azarbijan)
450
finished/delivered
2002/11/20 50
7
MALEKAN
NIGC (east Azarbijan)
NIGC (east Azarbijan)
360
finished/delivered
2002/11/6 75
8
RAMSAR
NIGC (Mazandran)
NIGC (Mazandran)
760
finished/delivered
2001/7/15 75
9
NOSHAHR (Phase 4)
NIGC (Mazandran)
NIGC (Mazandran)
360
finished/delivered
2002/11/15 61
10
TEHRANSAR gas supply
NIGC (Tehran)
NIGC (Tehran)
450
finished/delivered
2001/10/29 15
11
ROOD-HEN gas supply pipeline
NIGC (Tehran)
NIGC (Tehran)
360
finished/delivered
2001/10/2 40
12
AHAR gas distribution network (PC)
NIGC (east Azarbijan)
NIGC (east Azarbijan)
420
finished/delivered
2001/8/20 52
13
KOWSAR gas distribution network (phase 2)
NIGC (Ardabil)
NIGC (Ardabil)
360
finished/delivered
2000/10/17 15
14
ARDABIL gas supply and distribution pipeline
NIGC (Ardabil)
NIGC (Ardabil)
500
finished/delivered
1999/7/11 40
15
Addendum 1 NYAR+KALKHORAN distribution
NIGC (Ardabil)
NIGC (Ardabil)
350
finished/delivered
2002/6/30 30
16
Addendum 2 ARDABIL
NIGC (Ardabil)
NIGC (Ardabil)
1125
finished/delivered
2000/9/23 85
17
Addendum 3 ARDABIL
NIGC (Ardabil)
NIGC (Ardabil)
175
finished/delivered
2003/10/23 35
18
MESHKIN SHAHR gas supply and distribution (phase 1A)
NIGC (Ardabil)
NIGC (Ardabil)
180
finished/delivered
2000/5/13 30
19
MESHKIN SHAHR gas supply and distribution (phase 2A)
NIGC (Ardabil)
NIGC (Ardabil)
360
finished/delivered
1999/11/9 50
20
ISLAM SHAHR 3000 gas branches
NIGC (Tehran)
NIGC (Tehran)
360
finished/delivered
1998/12/20 30
21
Concrete storage for BOLOUR NOURI TAZEH
BOLOUR NOURI TAZEH
consulting engineers sadre sanat
180
finished/delivered
1998/7/16 -
22
Welldigging for cathodie protection of TEHRAN NIGC
NIGC (Tehran)
NIGC (Tehran)
180
finished/delivered
2000/10/4 -
23
HOSSEIN ABAD and MEHRSHAHR (phase 5)
NIGC (Tehran)
NIGC (Tehran)
180
finished/delivered
2000/11/12 40
24
Mobilization buildings for concrete works of MAJLIS (iranian parlemant)
consulting engineers polmir
consulting engineers polmir
400
finished/delivered
1996/8/31 -

 