ITEM |
Projects |
Employer |
Engineering Co |
Duration (Days) |
Progress |
Contract Start Date |
Pipe Length (KM) |
| 1 |
Construction of 14" Oil Transmission Pipeline Rey-Ghoochak |
NIOEC |
NIOEC |
270 |
in execution |
2006/6/20 |
48 |
| 2 |
Engineering , Procurement and Constructon (EPC) 36" TABRIZ-MIANDOAB (phase 1) |
East Azarbijan Province |
NILPAY Engineering co. |
500 |
finished/delivered |
2005/7/27 |
84 |
| 3 |
Gas Distribution and branches (LAMERD City) |
NIGC Fars Province |
NIGC - Fars Province |
450 |
finished/delivered |
2005/5/1 |
220 |
| 4 |
MOJEN-SHAHROOD transfer pipeline and related branches (PC) |
NIGC Semnan |
NIGC - Shahrood Province |
350 |
finished/delivered |
2003/6/21 |
42 |
| 5 |
BONAB transfer pipeline and distribution |
NIGC (east Azarbijan) |
NIGC (east Azarbijan) |
360 |
finished/delivered |
2004/3/4 |
50 |
| 6 |
SHABESTAR |
NIGC (east Azarbijan) |
NIGC (east Azarbijan) |
450 |
finished/delivered |
2002/11/20 |
50 |
| 7 |
MALEKAN |
NIGC (east Azarbijan) |
NIGC (east Azarbijan) |
360 |
finished/delivered |
2002/11/6 |
75 |
| 8 |
RAMSAR |
NIGC (Mazandran) |
NIGC (Mazandran) |
760 |
finished/delivered |
2001/7/15 |
75 |
| 9 |
NOSHAHR (Phase 4) |
NIGC (Mazandran) |
NIGC (Mazandran) |
360 |
finished/delivered |
2002/11/15 |
61 |
| 10 |
TEHRANSAR gas supply |
NIGC (Tehran) |
NIGC (Tehran) |
450 |
finished/delivered |
2001/10/29 |
15 |
| 11 |
ROOD-HEN gas supply pipeline |
NIGC (Tehran) |
NIGC (Tehran) |
360 |
finished/delivered |
2001/10/2 |
40 |
| 12 |
AHAR gas distribution network (PC) |
NIGC (east Azarbijan) |
NIGC (east Azarbijan) |
420 |
finished/delivered |
2001/8/20 |
52 |
| 13 |
KOWSAR gas distribution network (phase 2) |
NIGC (Ardabil) |
NIGC (Ardabil) |
360 |
finished/delivered |
2000/10/17 |
15 |
| 14 |
ARDABIL gas supply and distribution pipeline |
NIGC (Ardabil) |
NIGC (Ardabil) |
500 |
finished/delivered |
1999/7/11 |
40 |
| 15 |
Addendum 1 NYAR+KALKHORAN distribution |
NIGC (Ardabil) |
NIGC (Ardabil) |
350 |
finished/delivered |
2002/6/30 |
30 |
| 16 |
Addendum 2 ARDABIL |
NIGC (Ardabil) |
NIGC (Ardabil) |
1125 |
finished/delivered |
2000/9/23 |
85 |
| 17 |
Addendum 3 ARDABIL |
NIGC (Ardabil) |
NIGC (Ardabil) |
175 |
finished/delivered |
2003/10/23 |
35 |
| 18 |
MESHKIN SHAHR gas supply and distribution (phase 1A) |
NIGC (Ardabil) |
NIGC (Ardabil) |
180 |
finished/delivered |
2000/5/13 |
30 |
| 19 |
MESHKIN SHAHR gas supply and distribution (phase 2A) |
NIGC (Ardabil) |
NIGC (Ardabil) |
360 |
finished/delivered |
1999/11/9 |
50 |
| 20 |
ISLAM SHAHR 3000 gas branches |
NIGC (Tehran) |
NIGC (Tehran) |
360 |
finished/delivered |
1998/12/20 |
30 |
| 21 |
Concrete storage for BOLOUR NOURI TAZEH |
BOLOUR NOURI TAZEH |
consulting engineers sadre sanat |
180 |
finished/delivered |
1998/7/16 |
- |
| 22 |
Welldigging for cathodie protection of TEHRAN NIGC |
NIGC (Tehran) |
NIGC (Tehran) |
180 |
finished/delivered |
2000/10/4 |
- |
| 23 |
HOSSEIN ABAD and MEHRSHAHR (phase 5) |
NIGC (Tehran) |
NIGC (Tehran) |
180 |
finished/delivered |
2000/11/12 |
40 |
| 24 |
Mobilization buildings for concrete works of MAJLIS (iranian parlemant) |
consulting engineers polmir |
consulting engineers polmir |
400 |
finished/delivered |
1996/8/31 |
- |